Production and Operations Management :MCQ-3
101. We identified
several internal benefits of objectives, goals and a sense of mission. Which is
not included?
- Basis of plans and decisions
- Unity of direction
- Basis to resolve disputes
- None of the above.
Correct
answer: (C) Basis to resolve disputes
102. Identify the best
definition of planning.
- The core activity of planners and planning
departments.
- Setting an organisation's objectives and the
means of reaching them.
- Devising ways of achieving the objectives of
an organisation.
- An integrated process in which plans are
formulated, carried out and controlled.
Correct
answer: (B) Setting an organisation's objectives and the means of reaching
them.
103. Business cycle,
price trends, National Economy are ___________
- Micro Factors
- Macro Factors
- Controllable Factors
- All of these
Correct
answer: (B) Macro Factors
104. Which is not a part
of 5R's of buying?
- Right Quality
- Right Quantity
- Right Source
- None of the above
Correct
answer: (D) None of the above
105. Buying of the
annual requirements of an item during its season.
- Seasonal Buying
- Hand to mouth buying
- Scheduled Buying
- Tender Buying
Correct
answer: (A) Seasonal Buying
106. __________________
is concerned with the branch of economics relating the behavior of principals
and their agents.
- Financial management
- Profit maximization
- Agency theory
- Social responsibility
Correct
answer: (C) Agency theory
107. Corporate
governance success includes three key groups. Which of the following represents
these three groups?
- Suppliers, managers, and customers.
- Board of Directors, executive officers, and
common shareholders.
- Suppliers, employees, and customers.
- Common shareholders, managers, and employees.
Correct
answer: (B) Board of Directors, executive officers, and common shareholders.
108. _________________
also called part lists or building lists is the document generated at the
design stage.
- MRP (Material Requirement Planning)
- BOM (Bill of Materials)
- MPS (Master Production Schedule)
- None of these
Correct
answer: (B) BOM (Bill of Materials)
109. Purchasing
responsibilities can be divided into Buying, Clerical and __________________
division.
- Packing
- Traffic
- Record
- Follow up
Correct
answer: (B) Traffic
110. ________________________
are the basic materials which have not undergone any conversion since their
receipt from suppliers.
- WIP
- Raw Material
- Finished Parts
- Work Made Parts
Correct
answer: (B) Raw Material
111. Which of the
following statements is correct regarding profit maximization as the primary
goal of the firm?
- Profit maximization considers the firm's risk
level.
- Profit maximization will not lead to
increasing short-term profits at the expense of lowering expected future
profits.
- Profit maximization does consider the impact
on individual shareholder's EPS.
- Profit maximization is concerned more with
maximizing net income than the stock price.
Correct answer:
(D) Profit maximization is concerned more with maximizing net income than the
stock price.
112. __________________
is concerned with the maximization of a firm's stock price.
- Shareholder wealth maximization
- Profit maximization
- Stakeholder welfare maximization
- EPS maximization
Correct
answer: (A) Shareholder wealth maximization
113. ___________________
is the scientific technique for planning the ordering and usage of materials at
various levels of production and for monitoring the stocks during these
transaction.
- MPS
- MRP
- BOM
- None of these
Correct
answer: (B) MRP
114. Procuring an item
in staggering deliveries according to the delivery schedule finished to the
supplier by the buyer.
- Seasonal Buying
- Hand to mouth buying
- Scheduled Buying
- Tender Buying
- Speculative Buying
Correct
answer: (C) Scheduled Buying
115. Which of the
following statements is not correct regarding earnings per share (EPS)
maximization as the primary goal of the firm?
- EPS maximization ignores the firm's risk
level.
- EPS maximization does not specify the timing
or duration of expected EPS.
- EPS maximization naturally requires all
earnings to be retained.
- EPS maximization is concerned with maximizing
net income.
Correct
answer: (D) EPS maximization is concerned with maximizing net income.
116. __________________
is the time that elapses between issuing replenishment order and receiving the
material in stores.
- Replenishment time
- Lead time
- Idle time
- All of these
Correct
answer: (B) Lead time
117. __________________
is concerned with the maximization of a firm's earnings after taxes.
- Shareholder wealth maximization
- Profit maximization
- Stakeholder maximization
- EPS maximization
Correct
answer: (B) Profit maximization
118. The first activity
of Purchasing cycle is
- Communicating requirement to the purchase
- Source Selection and development
- Recognizing the need for procurement
- Inspection of goods
Correct
answer: (C) Recognizing the need for procurement
119. What is the most
appropriate goal of the firm?
- Shareholder wealth maximization.
- Profit maximization.
- Stakeholder maximization.
- EPS maximization.
Correct
answer: (A) Shareholder wealth maximization.
120. __________________
is the task of buying goods of right quality, in the right quantities, at the
right time and at the right price.
- Supplying
- Purchasing
- Scrutinizing
- None of these
Correct
answer: (B) Purchasing
121. Buying according to
the requirements is called
- Seasonal Buying
- Hand to mouth buying
- Scheduled Buying
- Tender Buying
Correct
answer: (B) Hand to mouth buying
122. Raw Materials and
WIP can be classified under
- Indirect Material
- Direct Material
- Finished Material
- Standard Parts
Correct
answer: (B) Direct Material
123. ___________________
establishes the overall production, workforce, and inventory levels.
- Production activity control
- Distribution requirements planning
- Master production schedule
- Sale and operations planning
Correct
answer: (D) Sale and operations planning
124. The master
production schedule requires all of the following input except
- Projected inventory levels
- Production quantities
- Forecasted demand
- All of the above are inputs into MSP.
Correct
answer: (D) All of the above are inputs into MSP.
125. In a distribution
requirements planning environment, forecasted demand at the plant level is
equal to __________________ in the distribution centre level.
- Scheduled receipts
- Planned receipts
- Planned orders
- None of the above
Correct
answer: (C) Planned orders
126. The difference
between a gross material requirements plan (gross MRP) and a net material
requirements plan (net MRP) is
- The net MRP includes consideration of the
inventory on hand, whereas the gross MRP does not.
- The gross MRP doesn't take taxes into account,
whereas the net MRP includes the tax considerations.
- The gross MRP may not be computerized, but the
net MRP must be computerized.
- The gross MRP includes consideration of the
inventory on hand, whereas the net MRP does not.
Correct
answer: (A) The net MRP includes consideration of the inventory on hand,
whereas the gross MRP does not.
127. An MRP system that
provides feedback to the capacity plan, master production schedule, and
production plans is called
- System nervousness.
- Closed-loop mrp.
- Lot-sizing.
- Load report.
Correct
answer: (B) Closed-loop mrp.
128. ___________________
determines when specific products will be produced, when specific customer
orders will be fulfilled, and what capabilities remain available to satisfy
unexpected demand.
- Sale and operations planning
- Material requirements planning
- Distribution requirements planning
- Master production schedule
Correct
answer: (D) Master production schedule
129. __________________
is the amount of new orders necessary to support production of the required
output in the next higher level in the bill of materials.
- Scheduled receipts
- Available to promise
- Projected ending inventory
- Planning horizon
Correct
answer: (A) Scheduled receipts
130. __________________
allows a segment of the master schedule to be designated as "not to be
rescheduled."
- Pegging
- Regenerative MRP
- Time fence
- System nervousness
Correct
answer: (C) Time fence
131. __________________
calculates the timing and quantities of material orders needed to support the
master schedule.
- Sale and operations planning
- Distribution requirements planning
- Material requirements planning
- Master production schedule
Correct
answer: (C) Material requirements planning
132. Which of the
following lot-sizing techniques is likely to prove the most complex to use?
- Part period balancing (PPB)
- The Wagner-Whitin algorithm
- Economic order quantity (EOQ)
- Lot-for-lot
Correct
answer: (B) The Wagner-Whitin algorithm
133. __________________
is a time phased approach to managing the physical distribution environment
with dependent demand logic.
- Master production schedule
- Distribution requirements planning
- Sale and operations planning
- Material requirements planning
Correct
answer: (B) Distribution requirements planning
134. The list of
quantities of components, ingredients, and materials required to produce a
product is the
- Bill-of-materials.
- Engineering change notice.
- Purchase order.
- Master schedule.
Correct
answer: (A) Bill-of-materials.
135. When a
bill-of-materials is used in order to assign an artificial parent to a
bill-of-materials, it is usually called a
- Phantom bill-of-materials.
- Planning bill-of-materials.
- Modular bill-of-materials.
- Pick list.
Correct
answer: (B) Planning bill-of-materials.
136. __________________
can be seen as the amount of new inventory created by production.
- Scheduled receipts
- Gross requirements
- Planning horizon
- Available to promise
Correct
answer: (D) Available to promise
137. A lot-sizing
technique that generates exactly what was required to meet the plan is
- The Wagner-Whitin algorithm.
- Economic order quantity.
- Lot-for-lot.
- Part period balancing.
Correct
answer: (C) Lot-for-lot.
138. The operations
manager has several tools available to deal with MRP system nervousness. Those
tools are
- Pseudo bills and kits.
- Time fences and pegging.
- Buckets with back flush.
- Net and gross requirements.
Correct
answer: (B) Time fences and pegging.
139. __________________
is the amount of materials necessary to support production of the required
output in the next higher level in the bill of materials.
- Planning horizon
- Available to promise
- Net requirements
- Gross requirements
Correct
answer: (D) Gross requirements
140. Breaking up the
order and running part of it ahead of schedule is known as
- Operations splitting.
- Lot splitting.
- Pegging.
- Overlapping.
Correct
answer: (B) Lot splitting.
141. A phantom
bill-of-materials is a bill-of-materials developed for
- A subassembly that exists only temporarily.
- A final product for which production is to be
discontinued.
- The purpose of grouping subassemblies when we
wish to issue "kits" for later use.
- A module that is a major component of a final
product.
Correct
answer: (A) A subassembly that exists only temporarily.
142. The master
production schedule is the schedule of production for what level
product/material?
- Level 0
- Level 1
- Level 2
- Level 3
Correct
answer: (A) Level 0
143. Managers can use
work standards in which of the following ways?
- Scheduling
- Motivating workers
- Capacity planning
- All of the above
Correct
answer: (A) Scheduling
144. Work-sample test
- Often use in-tray or in-basket exercises for
selecting shop floor workers
- Normally make use of many different
complementary predictors
- Require candidates to conduct a sample of the
work required for the job
- Do not necessarily have any obvious link with
the job in question
Correct
answer: (C) Require candidates to conduct a sample of the work required for the
job
145. Formal methods of
work measurement exclude which of the following?
- Time study method
- Work sampling method
- Predetermined data approach
- Systems approach
Correct
answer: (D) Systems approach
146. The work
measurement method that is not usually used for setting standards for
repetitive,'well-defined jobs is:
- The elemental standard data approach
- The predetermined data approach
- The time study method
- The work sampling method
Correct
answer: (D) The work sampling method
147. Looking at
socio-technical systems, which job design principle is not important?
- Skill variety
- Feedback
- Task autonomy
- None of the above (all are important)
Correct
answer: (D) None of the above (all are important)
148. Which of the
following is not a major personnel selection method?
- Graphology
- References
- Bio-data
- Focus groups
Correct
answer: (D) Focus groups
149. Which is not an
advantage of specialization?
- Upstream and downstream quality control
- Rapid training
- Ease of recruiting
- No education required
Correct
answer: (A) Upstream and downstream quality control
150. Which of the
following are reasons why an allowance should be added to determine the
standard time?
- Unavoidable delay
- Rest period
- Fatigue
- All of the above
Correct
answer: (D) All of the above
Comments
Post a Comment